Transperth C-series train

Transperth C-series train

Type of Transperth train


The Transperth C-series trains are a class of electric multiple units part of Alstom's X'Trapolis family of trains for Transperth that are being delivered as part of Metronet. The trains are operating on Perth's suburban rail network and entered service on the Joondalup and Mandurah lines on 8 April 2024.

Quick Facts In service, Manufacturer ...

History

In April 2018, the Public Transport Authority called for expressions of interest to build 41 6-carriage electric multiple units.[3][4] Three consortia were shortlisted to bid:[5][6]

On 18 August 2019, Alstom was announced as the successful bidder.[7] The trains will be assembled in Bellevue. Twenty-five sets will be delivered to provide rolling stock for network extensions as part of the Metronet project, while the other sixteen will replace the A-series stock from 2024.[8]

Transperth C-series train (left) with its predecessor Transperth A-series train (right) in 2023

In December 2019, Alstom released details of the contract and early renders of what the new trains will look like. Under the contract, worth approximately €800 million (AUD1.3 billion), Alstom will be responsible for the design, supply, manufacturing, testing and commissioning of 41 six-car electric-multiple-unit (EMU) trains for suburban services and two, three-car diesel-multiple-unit (DMU) trains for the Australind, which includes 50% local content, twenty years maintenance of the EMU trains and maintenance support services for the DMU trains.[9]

From 3 April to 18 April 2021, a two thirds length mock-up of a single carriage was made available for the general public to view and provide feedback at Yagan Square. Notable features of the new trains include a mixture of high back seats and bench seating, graphical passenger information displays, USB ports and hard-worn flooring instead of the carpet-laid floors of previous trains.[2]

On 7 June 2021 (Western Australia Day), the Railcar Manufacturing and Assembly Facility was officially opened at the Bellevue Railcar Depot, and handed over to Alstom to commence manufacturing the trains.[10][11][12] The first train was revealed on 14 August 2022, with twelve months of testing along the Joondalup and Mandurah lines set to occur before they are put in passenger service.[13][14] Testing along the Joondalup line between Clarkson station and Butler station commenced on 23 December 2022.[15]

The trains entered service on the Joondalup and Mandurah lines on 8 April 2024. A commemorative "first journey" occurred the day before on April 7, with tickets to that open to the public via a lottery.[16][17]


References

  1. "Dellner Australia's Footprint" (PDF). Dellner. p. 9. Archived (PDF) from the original on 19 March 2023. Retrieved 20 March 2023.
  2. "Signed, sealed, delivered from 2022 – Perth's new C-series trains". Metronet. 11 December 2019. Archived from the original on 9 March 2020. Retrieved 10 May 2020.
  3. "$1.6 billion for WA-based train build". Rail Express. 24 April 2018. Archived from the original on 24 April 2018. Retrieved 5 September 2019.
  4. "Perth launches RFQ for new train fleet". International Railway Journal. 25 April 2018. Archived from the original on 16 September 2021. Retrieved 16 September 2021.
  5. "Three bidders shortlisted for Perth EMU contract". International Railway Journal. 31 August 2018. Archived from the original on 16 September 2021. Retrieved 16 September 2021.
  6. "Three bidders prequalify for Perth EMU order". Metro Report International. 31 August 2018. Archived from the original on 16 September 2021. Retrieved 16 September 2021.
  7. Minister for Transport (18 August 2019). "Made in WA: Metronet railcars to be proudly built in WA". Archived from the original on 5 September 2019. Retrieved 5 September 2019.
  8. "Alstom to supply next generation of EMUs to Perth". Metro Report International. 20 August 2019. Archived from the original on 13 September 2021. Retrieved 16 September 2021.
  9. "Alstom to locally manufacture and maintain PTA's C-series trains for Perth's growing rail network". Alstom. 10 December 2019. Archived from the original on 12 December 2019. Retrieved 12 December 2019.
  10. "McGowan Government returns railcar manufacturing to WA". Media Statements. Archived from the original on 7 June 2021. Retrieved 7 June 2021.
  11. Law, Peter. "Mark McGowan and Transport Minister Rita Saffioti open Metronet Railcar Facility at Bellevue". The West Australian. Archived from the original on 8 June 2021. Retrieved 8 June 2021.
  12. "Railcar manufacturing returns to Western Australia". Metronet. Archived from the original on 8 June 2021. Retrieved 8 June 2021.
  13. "Locally manufactured trains back on the network after 30 years". Media Statements. 14 August 2022. Archived from the original on 14 August 2022. Retrieved 15 August 2022.
  14. Hiatt, Bethany (14 August 2022). "Metronet: WA's first locally-manufactured train in 30 years has been unveiled". The West Australian. Archived from the original on 15 August 2022. Retrieved 15 August 2022.
  15. "First C-series train on track as testing begins along network". Media Statements. 23 December 2022. Archived from the original on 23 December 2022. Retrieved 23 December 2022.
  16. Zimmerman, Josh (19 March 2024). "C-series Metronet train due to enter service next month". The West Australian. Retrieved 19 March 2024.
  17. "All aboard! First METRONET C-series train ready for passengers". Media Statements. 19 March 2024. Retrieved 19 March 2024.

Share this article:

This article uses material from the Wikipedia article Transperth_C-series_train, and is written by contributors. Text is available under a CC BY-SA 4.0 International License; additional terms may apply. Images, videos and audio are available under their respective licenses.