The Merta Road–Rewari line or Merta Road–Phulera–Rewari line is a railway route on the North Western Railway zone of Indian Railways. This route plays an important role in rail transportation of Bikaner division, Ajmer division and Jaipur division of Rajasthan state and Gurugram division of Haryana state.

Quick Facts Merta Road–Rewari line with Ratangarh, Merta City, Parbatsar and Jaipur–Churu branch lines, Overview ...

The corridor passes through the Desert Area of Rajasthan and Haryana with a stretch of 368 km with consists of four branch lines. The first branch line starts at Degana Junction and ends at Ratangarh Junction with a stretch of 153 km. The second branch line starts at Jaipur Junction, passes through Ringas Junction, and ends at Churu Junction with a stretch of 201 km. The third branch line starts at Merta Road Junction and ends at Merta City with a length of 15 km. The fourth branch line starts from Makrana Junction to Parbatsar City with a length of 22 km.

History

The main railway line from Merta Road Junction to Rewari Junction was originally built by Jodhpur–Bikaner Railway and Jaipur State Railway company of Bikaner Princely State, Jodhpur Princely State and Jaipur Princely State portion as metre-gauge line during the 19th and 20th century. This line was opened in different phases during the construction period.

  • The first phase, from Merta Road to Kuchaman City was opened on 13 March 1893.
  • The second phase, from Kuchaman City to Phulera Junction which also called as Sambhar Salt Lake Branch line was opened on 20 December 1879.
  • The third phase, from Phulera Junction to Narnaul was opened on 18 May 1905.
  • The fourth phase, from Narnaul to Rewari Junction was opened on 1 March 1941.

Whereas, the first branch line between Merta Road to Merta City was opened on 18 January 1905, and the second branch line between Degana Junction and Ratangarh Junction was built by the two companies in three sections such as Degana Junction to Marwar Frontier under the Jodhpur State Railway was opened on 16 September 1909 and under the Bikaner State Railway the two sections which are Marwar Frontier to Sujangarh section was also opened on 16 September 1909 whereas the Sujangarh to Ratangarh Junction section was opened on 2 February 1910.[1][incomprehensible] Later the third branch line between Makrana and Parbatsar City was opened on 1 August 1928, and thereafter fourth branch line from Jaipur to Churu Junction which comes under the Jaipur State Railway section was opened in different phases during the construction period.[2]

  • The first phase, from Jaipur Junction to Ringas Junction was opened on 19 December 1916.
  • The second phase, from Ringas Junction to Palsana was opened on 6 April 1918.
  • The third phase, from Palsana to Sikar Junction was opened on 1 December 1922.
  • The fourth phase, from Sikar Junction to Fatehpur Shekhawati was opened in 1943.
  • The fifth phase, from Fatehpur Shekhawati to Churu Junction was opened in 1957.[3]

After that, the conversion into 5 ft 6 in (1,676 mm) broad gauge was started in 1992-93[4] through into different section starting from the first section between Merta Road Junction to Phulera Junction was completed and opened in 1996,[5] later the second section between Phulera Junction and Rewari Junction which is also called as Phulera–Rewari chord section line was opened on 15 January 2009.[6]

Whereas, the Merta Road Junction–Merta City branch line was converted into 5 ft 6 in (1,676 mm) broad gauge and opened on 24 October 1994 with inaugurating the first Railbus in India as well as Asia also by Former Minister Nathuram Mirdha showing the green flag.[7] and the Makrana Junction–Parbatsar City branch line was also converted to 5 ft 6 in (1,676 mm) broad gauge and opened on 1 June 2016.[8] on the other side the Degana Junction–Ratangarh Junction branch line was also opened on 25 June 2010,[9] and the Jaipur–Churu branch line was closed on 15 November 2015[3] for conversion into 5 ft 6 in (1,676 mm) broad gauge in different phases and reverse way.

  • The first phase, from Churu Junction to Sikar Junction was opened on 9 December 2017.[10]
  • The second phase, from Sikar Junction to Ringas Junction was opened on 27 January 2019.[11]
  • The third phase, from Ringas Junction to Jaipur Junction was opened on 21 October 2019.[12]

Electrification

Electrification was started on 15 March 2016, on the first main line section between Phulera and Rewari [13] which was completed in 2018.[14] The Ringas Jaipur branch line section, which was approved on Rail Budget 2016-17, was also electrified in March 2021.[15] whereas the remaining sections of this route is fully electrified.

Trains passing through this line

Main

Branch


References

  1. "Indian Railways history". Retrieved 6 November 2012.
  2. "Written answers to Question asked in Parliament". Railway expansion programme in Rajasthan. Government of India. Retrieved 7 May 2014.
  3. "Railway Crisis in Jodhpur Division". Rajeev Shrivastava. IRFCA. Retrieved 17 May 2021.
  4. "Jaipur Division". North Western Railway. Retrieved 17 July 2021.
  5. "RATE ADVICE No 2 OF 2010" (DOC). North Western Railway. Jaipur. 30 June 2010. Retrieved 31 January 2020.
  6. "Achievements of NWR" (PDF). North Western Railway. Jaipur. 1 March 2019. Retrieved 31 January 2020.

Share this article:

This article uses material from the Wikipedia article Merta_Road–Rewari_line, and is written by contributors. Text is available under a CC BY-SA 4.0 International License; additional terms may apply. Images, videos and audio are available under their respective licenses.