Innovation Center station

Innovation Center station

Washington Metro station


Innovation Center station (preliminary names Route 28, Herndon – Dulles East)[3][4] is a Washington Metro station in Fairfax County, Virginia on the Silver Line. It is located adjacent to the Virginia Center for Innovative Technology at the intersection of the SR 267 and SR 28 in McNair, near the Fairfax / Loudoun county line. Originally planned to begin operation in 2016,[5] the station opened on November 15, 2022.

Quick Facts General information, Location ...

Facilities for the station include two pedestrian bridges across SR 267, leading to bus bays and kiss and ride lots at both entrances, as well as parking for 2,000 cars at the south entrance.[6]

History

The station under construction in September 2016.

The Silver Line was developed in the 21st century to link Washington, D.C., by rail to Washington Dulles International Airport and the edge cities of Tysons, Reston, Herndon, and Ashburn.[7] It was built in two phases; the first phase, linking Washington, D.C., to Wiehle–Reston East, opened in 2014.[8] The funding and planning of Phase 2 through Dulles Airport continued while Phase 1 was being constructed. In 2012, the Loudoun County Board of Supervisors voted 5 to 4 to extend the line to Dulles Airport and into the county.[9] On April 25, 2013, the Phase 2 contract was issued at a cost of $1.177 billion.[10]

In April 2015, project officials pushed back the opening date for the station to late 2019, stating that stricter requirements for stormwater management caused much of the delay. Per officials, the line also had to incorporate improvements to the system's automated train controls that were a late addition to the project's first phase.[11] In August 2019, project officials reported that they expected construction on the second phase of the Silver Line to be completed by mid-2020.[12] The opening date was postponed to early 2021,[13] then to late 2021.[14] In February 2021, Metro announced that it would need five months to test the Phase 2 extension.[15][16] The Metropolitan Washington Airports Authority (MWAA) then announced that the Phase 2 extension should be substantially complete by Labor Day 2021,[17] although MWAA subsequently missed this deadline.[18]

MWAA declared the work on the rail line to be "substantially complete" in November 2021. However, WMATA estimated that it could take five months of testing and other preparations before passenger service could begin.[19] Simulated service testing began operating along the Phase 2 tracks in October 2022.[20][21][22] Phase 2 formally opened on November 15, 2022.[23]

Station layout

M Mezzanine Fare control, ticket machines, station agent
P
Platform level
Westbound toward Ashburn (Dulles International Airport)
Island platform
Eastbound toward Downtown Largo (Herndon)
G Street level Exit/entrance, buses

References

  1. Klavon, Dawn (February 14, 2023). "Everything You Need to Know About the Silver Line Extension". Northern Virginia Magazine. Retrieved July 3, 2023.
  2. "Metrorail Ridership Summary". Washington Metropolitan Area Transit Authority. Retrieved February 11, 2024.
  3. "Board of Supervisors Approves Proposed Silver Line Station Names". April 10, 2012. Archived from the original on May 15, 2012. Retrieved April 11, 2012.
  4. Hosh, Kafia (March 29, 2011). "Fairfax OKs names for new Metrorail stations". Washington Post. Retrieved March 29, 2011.
  5. Fox, Peggy (December 18, 2018). "The Metro's Silver Line is expected to open in 2020 in Loudoun County, Virginia". WUSA9. Retrieved January 1, 2019.
  6. "Silver Line Activation Plan" (PDF). WMATA. Archived from the original (PDF) on February 9, 2014. Retrieved June 28, 2014.
  7. III, Ashley Halsey; Aratani, Lori; Duggan, Paul (July 26, 2014). "All aboard! Metro's new Silver Line rolls down the tracks for the first time". Washington Post. ISSN 0190-8286. Retrieved November 16, 2022.
  8. Jacobson Moore, Erika (July 3, 2012). "Loudoun's In: Split Board Backs Silver Line Extension". Leesburg Today Media Services. Archived from the original on July 8, 2012. Retrieved July 9, 2012.
  9. Goldberg, The Associated Press, Jeff (April 28, 2015). "Final phase of Silver Line to Dulles delayed until 2019". WJLA. Retrieved December 13, 2020.{{cite web}}: CS1 maint: multiple names: authors list (link)
  10. Roussey/ABC7, Tom (August 6, 2019). "Airports Authority: Silver Line could be completed by April 2020". WJLA. Retrieved December 13, 2020.{{cite web}}: CS1 maint: numeric names: authors list (link)
  11. Roussey (ABC7), Tom (February 20, 2020). "Second phase of Metro Silver Line delayed again, will open spring 2021 at the earliest". WJLA. Retrieved December 13, 2020.{{cite web}}: CS1 maint: numeric names: authors list (link)
  12. "Silver Line Phase 2 Update" (PDF). WMATA. February 11, 2021. Retrieved September 6, 2021.
  13. Cushman & Wakefield Research (February 3, 2014). "Silver Line". Washington Business Journal. Retrieved September 6, 2021.
  14. "Your new Silver Line stations coming soon with a new Metrorail map". www.wmata.com. WMATA. Retrieved October 7, 2022.
  15. "Next Phase of Silver Line to Open Soon". NBC4 Washington. Retrieved October 7, 2022.
  16. "Metro launches Silver Line Extension with opening ceremony; welcomes customers to #RideSilver to six new stations" (Press release). Washington Metropolitan Area Transit Authority. November 15, 2022.