Chitral hydel power is a hydroelectric power station which is located on the right bank of Lutkho river and 5 Km upstream of Chitral city. The flow of Lutkho river was diverted by a 3.72 Km long channel. The power station is equipped with 2 units of 200 kW and 2 units of 300 kW each to cumulatively generate 1 MW of electricity. The power generated from the power station is being provided to the Chitral city through an 11 kV transmission line. The project was commissioned in 1975.[1]