Baltic_states_synchronization_with_UCTE

Baltic states synchronization with UCTE

Baltic states synchronization with UCTE

Electricity infrastructure project


Baltic states synchronization with UCTE is an international electricity transmission infrastructure project to synchronize the three Baltic states (Lithuania, Latvia and Estonia) with the Synchronous grid of Continental Europe, managed by ENTSO-E, and leave the IPS/UPS transmission system managed by the BRELL (Belarus, Russia, Estonia, Latvia, Lithuania) agreement.[1] The project is expected to be completed by February 2025.[2]

Quick Facts Location, Country ...

Importance

The electricity systems of Estonia, Latvia and Lithuania were integrated into the IPS/UPS following the Soviet occupation of the Baltic States. IPS/UPS is largely managed centrally by Moscow. The synchronization project will allow the three Baltic States to regain full control of their electricity networks and strengthen energy security.[3][4] According to the European Commission, the synchronization of Baltic States is a political and financial priority and therefore has allocated more than EUR 1.2 billion towards the funding of the project.[5]

History

In 2007 the Prime Ministers of the three Baltic States confirmed their strategic objective to become part of the continental European network.[4] In September 2018 an official application for expansion of the synchronous zone was submitted to ENTSO-E.[6] On 27 May 2019, an agreement was signed for the connection of the Baltic states to the Continental Europe synchronous electric power network operation zone.[6]

Proposals to speed up the process

The need for synchronization became more urgent after the Russian invasion of Ukraine in 2022. Lithuanian Prime Minister Ingrida Šimonytė announced that Lithuania is seeking to speed up the process of transition and leave BRELL transmission system before 2025 with expected finalized plan made public by the end of 2023.[7]

On 22 April 2023 a stress test was scheduled in the Baltic states to test the infrastructure and operate for a day outside the IPS/UPS BRELL circle.[8] Latvia and Estonia withdrew from testing, while Lithuania successfully conducted the test and concluded that the country is ready to join Synchronous grid of Continental Europe in 2024.[9] Estonia and Latvia proposed the synchronization with European grid to be delayed to 2025 due to infrastructure not being ready.[10] President of Lithuania Gitanas Nausėda continued to pressure both Estonia and Latvia to synchronize with continental Europe in 2024, without waiting until 2025.[5] Eventually, the countries agreed to synchronize no later than February 2025.[2]

Connections

On 9 December 2015, Poland and Lithuania was commissioned LitPol Link, which was the first direct connection between Baltic states and the European grid.[11] In 2018 another proposed link with Poland via Baltic Sea was announced, called Harmony Link.[12] The total investment planned for the Harmony Link project is around €680 million, of which €493 million will come from the Connecting Europe Facility.[13] The Baltic States also have connections with the Nordic electricity grid via Nordbalt and Estlink.

See also


References

  1. "Lithuanian president hopes Baltic countries will withdraw from BRELL, synchronize together". baltictimes.com. 24 April 2023. Retrieved 12 August 2023.
  2. ""Litgrid" pirmą kartą veikė visiškai savarankiškai – atliko izoliuoto darbo bandymą". delfi.lt (in Lithuanian). 22 April 2023. Retrieved 12 August 2023.
  3. ""Litgrid" baigė šalies elektros sistemos izoliuoto darbo bandymą". lrt.lt (in Lithuanian). 22 April 2023. Retrieved 12 August 2023.
  4. "About project – Harmony Link". Retrieved 28 February 2022.

Share this article:

This article uses material from the Wikipedia article Baltic_states_synchronization_with_UCTE, and is written by contributors. Text is available under a CC BY-SA 4.0 International License; additional terms may apply. Images, videos and audio are available under their respective licenses.